This week has seen more decisions being made and some very major changes to the conversion.
We decided to have the loft windows in the bathroom sandblasted. You can have them obscured but we did not want a pattern in the glass.
The vented soffit’s were installed. These allow the air to circulate which reduces the risk of damp. This also protects the rafters from rot.


The roof tile delivery arrived.


The roof tiles were lifted by a tile lift to the top of the house and stacked ready for installation.




The dorma was felted and battened.






The rafters were felted, battened and tiles stacked ready for installation.




The fascias were removed from the front of the house.




Heres a video of the front of the house.
Here is a video of the rear.
Whilst the roof was getting some much needed attention, the joinery company began installing the loft stairs. We went with Ingles & Son based in Hertfordshire.
The stair guy (George) arrived.
Here is a view of the landing of our house prior to the loft stair installation.




The stairs were installed over a three day period.






Heres a video of the first day.
The stair installation was completed.










The insulation is still going up (this does take some time).


The velux windows went in.
View of velux windows in rafters (front of house)
Here is a video of the inside of the conversion.
Don’t forget to come back next week to see how we are getting on.
Hope you all have a great week!
To view the first instalment click here.
To view the second instalment click here.
To view the third instalment click here.